The City of Phoenix Street Transportation Department will begin construction on a community-driven project to improve pedestrian and bicyclist safety along 56th Street from Thomas Road to Camelback Road.
CONSTRUCTION SCHEDULE
· Construction is scheduled to begin October 12, 2026, with anticipated completion in Fall 2028.
· Standard construction hours will be Monday through Friday, 7 A.M. to 4 P.M.
· Some night and weekend work may be scheduled when necessary to minimize impacts to the community.
· Construction will initially begin at the south end of the project, focusing on the area between Thomas Road and Indian School Road.
PROJECT IMPROVEMENTS
· New bicycle and pedestrian multi-use paths along both sides of 56th Street to provide safer and more accessible connections.
· A new storm drain system to improve drainage in the area.
· Improvements at the Exeter Boulevard intersection to improve safety and traffic flow.
· New curbs, gutters, sidewalks, and ADAcompliant ramps to improve accessibility.
· Traffic-calming features designed to encourage safer travel speeds and improve safety for people walking and bicycling.
· Traffic signal updates at five intersections, and landscaping improvements throughout the corridor.